Durgapur Power Project III (2x20 MW)

Durgapur Power Project III (2x20 MW) has been taken up by NSPCL in order to meet the future power requirement of Durgapur Steel Plant (DSP)

Investment approval for the project has been approved by NSPCL Board on 13.12.2016

EPC package has been awarded to M/S Isgec Heavy Engineering Limited on 13.12.2016

Commercial Operation Date of Unit I : February 2019 (26 months from Investment Approval)

Commercial Operation Date of Unit II : April 2019 (28 months from Investment Approval)